       Completed Projects
PEB Works
S.No. Name of Work / Scope of Work & Location Client Consultant / Architect Duration
1. Construction of Steel Structure Building and Ancillary Work of 400TPD Physical Refining Plant at MEO Refinery. Mapak Edible  Oils (Pvt.) Ltd.
­ -

Start: Oct 2008

Completed: March 2009
2. Supply & Installation of Pre-Engineered Building with Allied Works at Lubricant Manufacturing Terminal (LMT) Korangi, Karachi. Pakistan State Oil Company Limited.
The PEAK, Karachi

Start: Dec 2006

Completed: Feb 2007
3. Construction of PEB at Kotri, SITE. Two modules of 140’ x 400’ comprising of Warehouse and Manufacturing Units. HI-Tech Pipes & Engg. Industries
The PEAK, Karachi

Start: 2007

Completed: 2007
4. Construction of Pre-Engineered Steel Re-rolling Mill at Raiwind. Total covered area is 19000 m2. Gulf Nishat, Lahore
A.A Associates, Karachi

Started :May., 2006

Completed: 2006

5. Construction of Pre-Engineered Motor-Cycle Assembly Plant on EPC basis. HKF Engineering, Lahore
Civil & Urban Engineering, Lahore

Started :Feb. 2006

Completion: March 2006
6. Construction of Re-Vamp Project for Lube Oil Facilities, the job consist of Process Pipeline, Installation of Pumps, Instrumentation, Electrical Job, Construction of R.C.C Structure, Erection & Installation of Pre-Engineering Building, Racking System, etc. on PEC basis for PSO at Korangi near NRL, Karachi Pakistan State Oil Company LimitedPlanning Management Engineering International (Pvt.) Ltd., Lahore
Planning Management Engineering International (Pvt.) Ltd., Lahore

Started:Feb., 2003

Completion: June, 2004

 

 

7.

Erection & Installation of Pre-Engineering Buildings :

  1. Compressor Building
  2. Generator Building
  3. Workshop Building

or Jamshoro Joint Venture Limited.(JJVL.), Jamshoro

The Hanover Company, USA
The PEAK, Karachi

Started: Sep, 2004

Completed: Dec, 2004

 

8. Up gradation of tank wagon loading facilities at PSO Keamari Terminal – B, Karachi Pakistan State Oil Company Limited
Petrochem Engineering & Industrial Consultants, Karachi

Started : 2003

Completion : 2003
9. Mechanical Construction Works for Condensate Processing Facilities, Karachi

Enar Petrotech Services (Pvt.) Ltd.

--

Started : 2001

Completion : 2002
10.

Installation of pipeline System & fabrication / erection of steel structure gantry for improvement on loading / unloading facilities at Chakpirana Depot, Khariyan

Pakistan State Oil Company Limited
--

Started : 2000

Completion : 2001
11. Fabrication / Erection of Storage Tanks, Fire Water Tanks & Loading Gantry Adjacent to NRL Site, Karachi

Enar Petrotech Services (Pvt.) Ltd.

Contractor HMC
--

Started : 2000

Completion : 2001
12.

Installation, Erection of Gantry, Construction of Jet Fuel (JP4) &l execution of mechanical, E&I works at Fuel Farm Facility at Lahore International Airport, Lahore

Pakistan State Oil Company Limited

Enar Petrotech Services (Pvt.) Ltd.

Started : 2000

Completion : 2002
13.

Fabrication, Erection & Installation of Steel Structure and utility piping for Assembly Shop at plant No. 2, Sajawal

Dewan Farooq Motors
--

Started : 1999

Completion : 2000
14. Extension of Office in hall “A” of new lamp factory including Civil, Structure Steel Works, Plumbing Work at SITE Karachi Philips Electrical Industries Pakistan
Naqvi & Siddiqui Consultant Services

Started : 1998

Completion : 1998

   
 